Amur Mining and Chemical Combine LLC
On July 18, 2024, JSC Engineering Center GOChS Basis successfully completed factory acceptance tests of the SMIS equipment, including the SMIS subsystem of the facility: Infrastructure of the off-site facilities (buildings, cable networks) of the Amur Gas Chemical Plant. (SIBUR).
The tests were conducted from July 15 to July 19, 2024 in Krasnodar, the purpose of which was to check the compliance of the composition, functions and operational characteristics of the system with technical requirements, as well as to check the application software for its operability, correctness of its configuration and compliance with the project requirements.
The engineering staff of the customer, NHPA LLC, and the general designer, NIPIGAZ JSC, participated in the tests. This system is intended for the end user, Amur GCC LLC.